Department of Wildlife, Fisheries and Parks
Updated 09/29/2021
645-005: Percy Quinn Dam Repair (PLANNING)
Professional: Dungan Engineering, P.A.
Contractor: (GC001) Eutaw Construction Company, Incorporated
Projected Completion Date:
645-005: Percy Quinn Dam Repair (WARRANTY)
Professional: (PP002) Dungan Engineering, P.A.
Contractor: (GC001) Eutaw Construction Company, Incorporated
Projected Completion Date: September 17, 2013
645-005: Isaac-Percy Quinn Emergency Dam Repair (CONSTRUCTION)
Professional: (PP003) Dungan Engineering, P.A.
Contractor: (GC002) T.L. Wallace Construction, Inc.
Surety: Arch Insurance Company, Kathleen B. Scarborough, 300 Plaza Three, Jersy City, N.J. 07311 201-743-4000
Projected Completion Date:October 24, 2014
645-005: Isaac-Percy Quinn Emergency Dam Repair (PLANNING)
Professional: Dungan Engineering, P.A.
Contractor:
Projected Completion Date:
645-007: Simpson Dam Repairs (WARRANTY)
Professional: (PP001) Dungan Engineering, P.A.
Contractor: (GC001) Southern Rock, LLC
Surety:
Projected Completion Date: May 25, 2021
645-009: Holmes County Dam Repairs (Warranty)
Professional: (PP001) Dungan Engineering, P.A.
Contractor:
Surety:
Projected Completion Date: June 30, 2021
645-010: Prentiss Walker State Lake Dam Repairs (PLANNING)
Professional: (PP001) WGK, Inc.
Contractor:
Surety:
Projected Completion Date:
645-011: Shadow Lake Dam Repairs (PLANNING)
Professional: (PP001) Dungan Engineering, P.A.
Contractor: (GC001) S & S Excavation, LLC
Surety: The Gray Insurance Company, McGriff Insurance Services, Inc. 1020 Highland Colony Parkway Ste 302, Ridgeland, MS 39157 601-790-8500
Projected Completion Date: July 27, 2021
645-012: Tom Bailey Lake Dam Repairs (PLANNING)
Professional: (PP001) Dungan Engineering, P.A.
Contractor:
Surety:
Projected Completion Date:
For information on any of these projects, please contact the Professional listed above. Surety information is provided for projects under construction.