Sillers Building

 

360-041:  Communications - Sillers Building (Warranty)
Professional:  Information Technology Services (601) 359-1395
Contractors:  GC001 Lane-Tedder & Associates (601) 483-2222
GC002 (CP1) JSI Communications Division of James Self Inc.
GC003 (CP1)  Lane-Tedder & Associates, Inc.
Projected Completion Date:


360-043:  Relocation Costs – Sillers Building
Professional: 
Contractor:
Surety:
Projected Completion Date:

360-044:  Communications/Computer Infrastructure – Sillers Building (Construction)
Professional:  (OP001) Information Technology Services (ITS)
Contractor:  GC  Multiple
Projected Completion Date:

360-048:   Sillers Lobby Upgrades (WARRANTY)
Professional: (PP001) Eley Guild Hardy Architects - Jackson, P.A.
Contractor: (GC001) Cal-Mar Construction Company, LLC
Date of Completion: September 1, 2017

360-049:  Tenant Improvements (Access Control - 12th, 14th, and 17th Floors)  (BIDDING)
Professional: (PP001) JBHM Architects, P.A.
Contractor:  (GC001) S & L Commercial Builders, Inc.
Surety:Fidelity & Deposit Company of Maryland, Trina Cobb, 1299 Zurich Way, 5th Fl. Schaumburg, IL 60196-1056, 847-605-6000
Projected Completion Date: December 22, 2020

 

 